Commissioning Of Spring Cone Crusher

Commissioning Of Spring Cone Crusher
1. Empty-load commissioning Of Spring Cone Crusher
a) Before starting the cone crusher, the fasten situation of main joint parts must be checked.
b) Before starting the machine, start the oil pump at first. User may start the cone crusher until the lubrication is done.
c) Continue empty-load commissioning must be taken not less than 2 hours.
d) The empty-load commissioning should meet the following requires:
The self rotation revolution around centerline of the crushing cone can not exceed 15r/m.
No periodically noisy comes from the bevel gear.
Oil supply pressure is within 0.8-1.5kgf/cm2
Oil return temperature should not exceed 50ºC.
After commissioning, check the condition of each frictional parts.
e) If there is an unusual appears relating to the revolution, then shutdown the machine immediately, perform troubleshooting.
f) If there is a periodically noisy comes from bevel gear, then check the correctness of bevel gear installation.

2. Load commissioning Of Spring Cone Crusher
a) Once the empty-load commissioning has passed, load commissioning can be taken.
b) Load commissioning should be taken continually 24-48 hours.
c) When starting load commissioning, add few ores at first, then increase the amount gradually until the chamber is full.
d) The empty-load commissioning should meet the following requires:
No sudden vibration and noisy.
Feeding and discharging are normal.
Oil supply pressure is within 0.8-1.5kgf/cm2
Oil return temperature should not exceed 60ºC.
Electrical equipments control system works normally.

If you want to know more about our equipments details,please contact us
www.shuosencrusher.com
sarahzzdshj@gmail.com
sarah@shuosencrusher.com

评论

此博客中的热门博文

Common knowledge of mineral processing

How much is a set of quarry plant, what equipment does it use?

How to reduce the dust of jaw crusher