Operation Instructions of Jaw Crusher

Operation Instructions of Jaw Crusher
a) The preparation before starting:  
(1) Inspect each bearing to ensure whether it lubricates well, and whether there is enough lubricating grease on the toggle plate joints and bearing inners.
(2) Check carefully whether all fasteners are totally fastened.
(3) Check whether the drive belt is under good condition, and change the belt if any damages can be found. When there is grease contamination on the belt or bell wheel, it can be clean up with a clean dishcloth.
(4) Check whether the protective device is under good condition, if there are any unusual events and safety hazards conditions, should correct them and report.
(5) Check whether there are any ore or other impurities inside the crushing cavity.

b) The starting of the crusher  
(1) After inspecting the machine and transmission parts are under good condition, the machine may starts.
(2) This machine can only start under empty load conditions.
(3) After having started the machine, shut down the machine if there is any unusual event happens. After having found out the causes and fixed, the machine may restarts.  

c) Maintenance and operation
(1) When the crusher operates normally, material feeding can start afterwards.
(2) To be crushed materials should be evenly added into the crushing cavity, and should avoid feeding from side, in order to prevent sudden load change or sudden increasing of unilateral load.
(3) Under normal circumstances, the maximum temperature of the bearing should not exceed 75℃, otherwise, shut down the machine immediately, find out causes and be fixed.
(4) Before stopping the machine, the operation of material feeding should stop at first, when crushed materials are discharged completely from the crushing cavity, may shut down the power.
(5) If the machine stops caused by obstruction of materials inside the crushing cavity while in operation, please shut down the power immediately. The machine can be restarted after having discharged the materials.
(6) The head of the jaw plate is replaceable when it is worn.

d) Points for attention
(1) Everyone who operates this machine should has gone through the security and technical training.
(2) It is forbidden to look, adjust, clean up or overhaul from below to the inner of the machine while operating.
(3) It is forbidden to move mines by hand directly inside the feed inlet and machine cavity inlet while operating.
(4) The electric equipment of this machine should be earthed, and install wires inside insulating tube. 
http://www.shuosencrusher.com/
sarah@shuosencrusher.com
whatsapp:008613598023510

评论

此博客中的热门博文

Operation of Jaw Crusher

22 checking items in cone crusher operation

What factors affect the output of cone crusher